SFPUC contractor has started to clear out the brush and trees on the Right of Way in the area of Poplar Ave and Hess Rd. They will continue to work in this area and head towards Woodside Road, Locust, Hemlock and past Fleishman Park and Linden park.
Pipe will be delivered to the SFPUC Right of Way and installed, shortly after the clearing occurs.
Monday, August 30, 2010
Top of the Hill at Hillcrest Drive
We have reached the top of the hill at Hillcrest Drive in Redwood City. Pipe is being installed and trench has been back filled from Alameda to Esther.
Tuesday, August 24, 2010
BDPL5 being installed at Esther Lane
Monday, August 23, 2010
We are at Upland Road
We have passed Brewster and are installing pipe near Upland Road, Redwood City. Next stop is Esther Lane.
Friday, August 20, 2010
We are heading to Upland Rd and Esther Lane
We have crossed Alameda de las Pulgas and are installing pipe past Brewster Ave to Upland Rd and making our way to Esther Lane.
Friday, August 13, 2010
Saturday work in Redwood City!
There are several other places that we are going to be working this Saturday, August 14th.
- We are going to be on Quartz, James and St Francis Streets from 8am to 5pm (off hauling soil)
- On Avenue del Ora from 8am to 5pm (restoring roadway)
- Hawes Elementary School from 8am to 5pm (installing fencing)
Alameda de las pulgas crossing this weekend!