Thursday, October 18, 2012

Check out the MTBM Delivery Video!

Micro-tunneling and the hauling of excavated materials continues at the Jacking Pit side on Bennett Road, Redwood City. The Contractor has already advanced nearly 200ft of the 468ft tunnel. A 72” diameter pipe casing is inserted and welded as they micro-tunnel. The new drinking pipeline will be installed once the tunnel is complete.

Please note that Saturday work is scheduled for October 20th and 27th. Work hours are 8am to 5pm. On October 20th, the Contractor will have the tunnel machinery serviced so the microtunnel operation will not begin until midday.

Feel free to contact Public Outreach at 800-571-6610 if you have any questions.