Major grading and concrete work has taken place over the past several weeks to reform the landscape and replace the walkways. This work will continue while we reinstall play equipment and other park features over the next several weeks. Please continue to check the blog for updates and photos as we transform the North Fair Oaks Playground back into a community resource.
San Mateo County
- Continue work at the Pulgas Valve Vault (in Pulgas Open Space)
- Pipe installation is ongoing along Edgewood Road and Edmonds Road
- Final pipeline work continues at Ebener Street and Oak Avenue and progress to Hawes School
- Backfill and valve work at Redwood City Valve House on El Camino Real
- Pipe installation is complete under Highway 101 and additional work is continuing on both sides of the tunnel
- Pipe installation is continuing on Bay Road nearing Harmon Drive
Parks
- Restoration continues at Fleishman Park in Redwood City
- Restoration continues at Fair Oaks Community Playground
- Curb and gutter repair work continues at Dumbarton towards Pacific Avenue in North Fair Oaks
- Commercial parking lot restoration is finishing up on Woodside Road, Redwood City and starting this week restoration will begin in Menlo Park on O’Brien Drive
the project that never ends. Our neighborhoods have been ripped apart for over a year now. Looking back on the archives, we were supposed to have fences back in place last December (2010) but due to rain, construction was pushed out. A year later, we our streets and driveways are still destroyed, fences have yet to be replaced and there appears to be no end in site. What a shame!