Quest, a KQED show, this week featured the Water System Improvement Program (WSIP) for our Hetch Hetchy water system. Check out Quest's video segment about the infrastructure upgrades throughout the system.
Did you know that the water was first delivered to the Bay Area by Hetch Hetchy in 1934? For some more history, check out this video produced by the SFPUC in 1940 chronicling the initial construction of the Hetch Hetchy water system.
Construction Update
San Mateo County
- Continue work at the Pulgas Valve Vault (in Pulgas Open Space)
- Pipe installation is ongoing along Edgewood Road
- Near Hwy 280, pipe installation is crossing Crestview Drive
- Final pipeline work will commence at Ebener St and Oak Ave and progress to Hawes School.
- Backfill and valve work at Redwood City Valve House on El Camino Real
- The pipe casing is successfully installed, crews will begin pipe installation within tunnel under Highway 101
- Begin pipe installation on Bay Road now that potholing is complete here
Parks
- Continue restoring Fleishman Park in Redwood City
- Restoration of Fair Oaks Community Playground is ongoing
- Look for our table at the Re-opening of Flood Park this Saturday
- Curb and gutter repair work between 2nd Ave and 5th Ave in North Fair Oaks
- Commercial parking lot restoration in Redwood City at El Camino and Woodside Road
- Phase 1 fence installation is concluding in Redwood City near Topaz Street. Phase II is out for bid.
0 comments:
Post a Comment