Friday, July 30, 2010

Saturday work this weekend!

Pipe installed at Avenue Del Ora
There will be Saturday work from 8am to 6pm, on Avenue Del Ora and at Hawes School, in Redwood City.

Wednesday, July 28, 2010

Heading to Avenue del Ora!


We are crossing Jefferson Street and heading towards John Gill Elementary School on Avenue del Ora.

Working on Ivy Dr in Menlo Park!


You may have seen us on Ivy Drive this week.  We installed about 200 feet of pipe.

Thursday, July 22, 2010

Pipes delivered to Avenue Del Ora!


Pipes are delivered and ready to install on Avenue Del Ora, in front of John Gill Elementary School.

Crossing Jefferson St in Redwood City!

We are getting ready to cross Jefferson Street this Saturday, July 24th. Traffic will be impacted between the hours of 9 am to 6pm. Please drive carefully and safely.

Tuesday, July 20, 2010

Welders at work!



Welders have to connect all of the 40 foot sections of the Bay Division Pipeline.

Friday, July 16, 2010

Weekend Work this Saturday


MCI will be working this Saturday, July 17, in the parking lot behind Red Morton Park's Kiwanis Field, and on Myrtle Street between Madison and the parking lot. Work will take place from 8AM-4PM. Thanks as always for your patience during construction!

Thursday, July 15, 2010

We are heading toward Jefferson Avenue!

We are on Myrtle St and heading toward Jefferson Avenue, through the Kiwanis field. Starting Monday, July 19th, there will be lane closures and traffic detours on Jefferson Avenue, between Hawes Street and Nevada Street, at Avenue del Ora.

See the recent Press Release by Redwood City about this upcoming construction:

http://www.redwoodcity.org/manager/news/2010/pr_bit_jefferson_constr.html

Friday, July 9, 2010

Sat work in July!



As we continue to finish Hawes School Elementary, we are moving toward Red Morton Park. Please be aware that our crews will be working on some Saturdays to make sure that we finish before school starts in the Fall. This Saturday, July 10, we will be working in Red Morton Park on King St. Please be aware that King St will be closed during construction and detours will be posted. Stay tuned for more updates next blog.